1/29/03 Creative Loafing, Charlotte
Newspaper
Taken For A Ride?
The main consultants
for Mecklenburg's light rail system are big, powerful companies. They
also have a notorious history of scandal, massive cost overruns,
engineering snafus and deceiving the public.
BY TARA
SERVATIUS
The last time two of the consultants overseeing
Mecklenburg County's light rail and mass transit plan worked on a
large-scale project together, they were responsible for an 80-foot
sinkhole, thousands of lawsuits totaling over $1 billion, and a trail
of fraud and corruption so long that even the FBI couldn't untangle
it. Now they're advising Charlotte Area Transit Officials on our
transit plan and helping to design it.
The two design,
construction and engineering firms, Parsons Brinckerhoff Quade &
Douglas, Parsons Transportation Corp., and their smaller business
units are directly responsible for projects widely regarded as the
biggest transit debacles in the nation's history. Both have stark
histories of deceiving the public and government officials about the
true costs of transit projects, and then benefiting directly from
project cost overruns.
These histories are alarming enough to
call into question every figure, fact and cost estimate ever given to
the voters and elected officials of Charlotte-Mecklenburg by these
companies. And it's enough to make one wonder why the Metropolitan
Transit Commission and Charlotte City Council approved consultant
contracts with them in the first place.
Members of the MTC we
spoke to say they were unaware of the companies' past scandals, but
are determined to get answers from Charlotte Area Transit System
(CATS) CEO Ron Tober. CATS spokespersons said no one there was aware
of the companies' past scandals when the contracts were proposed.
It's still unclear who did background checks on the companies. (See
"What They're Saying" sidebar.)
Boston's Notorious
"Big Dig"
In 1998, before Parsons Brinckerhoff,
Quade & Douglas prepared Charlotte-Mecklenburg's first transit
plan for voter approval, the company, in a joint venture with another
firm called Bechtel Civil Inc., oversaw the design and construction
of Boston's Big Dig. The legendary project, a multi-billion dollar
effort to bury 7.5 miles of Boston's central artery roadway
underground, would eventually become the mother of all US
transportation project fiascos. While the project was highly complex
and didn't involve light rail like Charlotte-Mecklenburg's transit
plan does, the fraud and cost overruns that have come to be
associated with Big Dig have made national news -- and call into
question the corporate practices of the company that to date has
played a major guiding role in our own city's transit plan. In 1985,
when Bechtel-Parsons Brinckerhoff was hired to oversee it, the
project had an estimated cost of $2.6 billion and a completion date
of 1998. Today, the project has a projected completion date of 2005,
and its price tag has ballooned to $14.6 billion and climbing. And
that doesn't even count the millions of dollars various state and
federal agencies have spent on more than 15 separate investigations
of the project's managers, which included Bechtel-Parsons
Brinckerhoff, for shoddy design, construction and engineering, fraud
and corruption.
"You do have to monitor them,"
Massachusetts Former Secretary of Transportation Frederick Salvucci
told the Boston Globe about Bechtel-Parsons Brinckerhoff in September
1994. "But the most important role of your monitoring is to make
sure that you're getting what you paid for, and yeah, you don't want
them going crazy on costs. You need a lot of public employees to do
that."
Three months later, a report released by
Massachusetts State Inspector General Robert Cerasoli's office proved
Salvucci right. The report blamed the state highway department and
Bechtel-Parsons Brinckerhoff for cost overruns and systematic
problems on the project. It also suggested that Bechtel-Parsons
Brinckerhoff and another contractor attempted to cover up costly
charges in several cases and presented incomplete and inaccurate
information to project officials about the work.
It would be
six more years before the truth about Big Dig would finally become
widespread public knowledge. In 2000 -- the year our local transit
officials and the Charlotte City Council awarded four contracts worth
$2.6 million to Parsons Brinckerhoff for transit advisory services
for CATS, the North and Northeast Corridor Major Investment studies,
pedestrian controls along the South Corridor, and North Corridor rail
assistance -- the company's reputation hit rock bottom in Boston.
Almost every month in 2000, there was one shocking revelation
or another about Big Dig.
It started with a report released
by State Auditor Joseph DeNucci in February of that year which
concluded that, because of failures by Bechtel-Parsons, at least $19
million was wasted on useless design work in the Fort Point Channel
section of the project because the company ignored concerns about
unusually soft soils in the area. Had DeNucci's earlier warnings to
transit officials to take cost control responsibilities away from
Bechtel-Parsons been heeded, things might have turned out
differently. Instead, DeNucci went on to make a career of sniping at
the Bechtel-Parsons and transit officials. In 11 other reports, he
documented $446 million in additional waste on the project because
cost-reduction methods weren't applied.
But by year's end,
DeNucci's findings would be dwarfed by reports and accusations of
large-scale corruption that reached the highest levels of government.
In April 2000, a Federal Highway Administration audit
concluded that Bechtel-Parsons and state officials misled the federal
government, which was funding part of the project, about $1.4 billion
in cost overruns. (The true figure was later discovered to be $2.2
billion.) That announcement prompted a US Senate probe overseen by
Sen. John McCain, who blistered Bechtel-Parsons' representatives
during hearings for open-ended cost hikes on the project. Not to be
left out of the action, a fraud and corruption investigation was
launched jointly that June by the FBI's Public Corruption Unit, the
Department of Labor, the Federal Highway Administration and the
Federal Department of Transportation. By the end of the month, the
Securities and Exchange Commission piled on as well, launching an
investigation into whether Big Dig officials and Bechtel-Parsons
failed to disclose the project's real cost to bond investors in
financial statements prepared in 1999.
When asked if the
company had a responsibility to inform the public about the true
costs of the project, a company spokesman who asked not to be named
told The Boston Globe that Bechtel-Parsons Brinckerhoff didn't have a
responsibility to share that information with anyone except their
clients, the Massachusetts Highway Department and the Massachusetts
Turnpike Authority.
In July, a whistleblower filed a federal
suit against Bechtel-Parsons Brinckerhoff, charging the companies had
made at least $10 million in false claims while billing the
government for costs.
The same month, a memo from Big Dig
project counsel Anthony Battelle surfaced indicating that Big Dig
officials and Parsons Brinckerhoff knew they may have been violating
the state's prevailing-wage law by underpaying truck drivers for more
than three years before they were forced to add $20 million to the
project budget to pay them back wages. (When the scandal broke in
1996, Bechtel-Parsons Brinckerhoff and state transportation
executives denied any knowledge of violating the law. The memo
proving otherwise was dated October 1, 1993.)
Then in August,
a Boston Herald investigation revealed that Massachusetts Governors
Paul Celluci and William Weld and numerous other state and city
politicians had had numerous relatives and cronies added to Big Dig's
payroll by getting them assigned to the payrolls of Bechtel-Parsons
Brinckerhoff and other subcontractors who then billed the state for
their salaries despite the fact that many of them didn't actually
show up for work. By October, Attorney General Tom Reilly had hired a
high-powered private international detective agency to help ferret
out corruption within Big Dig.
Things only got worse in 2001
-- the year Parsons Brinckerhoff was awarded two more transit
contracts totaling $1.8 million for work on Mecklenburg County's
transit system. In January 2001, a Massachusetts state inspector
general's report came out showing that Big Dig officials had done
little to recoup money from Bechtel-Parsons after mistakes by
engineers caused $83.5 million worth of change orders. The report
recommended that the Turnpike Authority cut ties with Bechtel-Parsons
Brinckerhoff, but by then it was too late. Transit officials had
already scrambled to renew Bechtel-Parsons' contract for another five
years.
It wasn't just the Turnpike Authority that
Bechtel-Parsons Brinckerhoff had somehow managed to wrap around its
finger. Another state inspector general's report released in March
showed the stunning reach of the company's political power and
influence.
According to the report, Big Dig project officials
and Bechtel-Parsons had conspired with state officials and the
Federal Highway Administration to hide the true $14 billion cost of
the project from the public, bond investors and Wall Street.
According to the inspector general's report, Bechtel-Parsons
accurately reported to then-governor Bill Weld in 1994 that the
project's true cost would be $13.8 billion.
"After
Bechtel-Parsons Brinckerhoff presented its $14 billion estimate in
1994, state managers directed state and Bechtel-Parsons Brinckerhoff
staff to undertake a cooperative effort to maintain the fiction of an
"on-time' and "on-budget' $8 billion project," the
report said. "Records show that they did so by applying a
largely semantic series of exclusions, deductions, and accounting
assumptions that covered up the $6 billion difference."
The
next month, Inspector General Robert Cerasoli released a 1995 memo
written by a budget manager at Bechtel-Parsons Brinckerhoff that
summarized instructions that Bechtel-Parsons received from
then-transportation secretary James Kerasiotes.
"It
should be noted that Secretary Kerasiotes at the Federal Highway
Administration briefing stated that he expected this value to be
below $8.0 billion prior to releasing to the public," the memo
read. Not surprisingly, the cost figure officially unveiled to the
public was $7.997 billion.
That revelation sheds new light on
a July 2002 report in the Charlotte Observer headlined "Price
Tag of Transit is Soaring, Projections More Than Double, Critics Say
the Public Was Had," in which the paper reported that it was
still a mystery why the original cost estimate for our transit plan
drawn up by Parsons Brinckerhoff Quade & Douglas did not account
for inflation, despite the fact that former Charlotte City Council
members Mike Jackson and Don Reid repeatedly questioned whether it
had been factored in.
At the time, Parsons Brinckerhoff
didn't return the Observer's calls for comment. When Creative Loafing
tried to get a comment from the company on this oversight, we were
referred back and forth between their Charlotte and Raleigh offices.
The only Parsons Brinckerhoff official willing to talk to about the
situation, a manager from the Raleigh office who asked that his name
not be used, said that the employee who oversaw the project is no
longer with the company and no one knows why inflation wasn't
factored in.
Despite the confusion over the real cost of the
project, in 2002, the company was awarded two more contracts by
Charlotte City Council totaling $3.5 million for work on CATS' New
Bus Maintenance Facility and a transit-oriented development workshop.
Meanwhile, in Boston, the Turnpike Authority board of
directors also awarded contracts to two consultant groups. Their job,
as described in the Boston Herald, was to act as "independent
watchdogs" and to "baby-sit" Bechtel-Parsons
Brinckerhoff for the remainder of the Big Dig project.
Flirting
with Disaster In LA
Before the Big Dig officially went bad in
Boston, Parsons Brinckerhoff Quade & Douglas was up to its knees
in trouble on the other side of the country. In 1995, the world
watched as a massive sinkhole swallowed 80 feet of Hollywood
Boulevard and buildings began to crack, buckle and sink several
inches. In its wake, more than 1,000 lawsuits totaling more than a
billion dollars in damages were filed against the Metropolitan
Transit Authority (MTA) by angry business and property owners. When
the dust cleared, a forensic engineering firm hired by the MTA
reported that EMC, an engineering partnership between principal
partners Parsons Brinckerhoff Quade & Douglas and a company
called Daniel Mann Johnson & Mendenhall, had signed off on the
faulty digging plan blamed for the disaster.
A former tunnel
digger, Rocky Woody, who was employed by one of the subcontractors on
the job, told the New Times of Los Angeles that he was amazed by the
problems Parsons-Dillingham inspectors ignored.
"They
sat right up there the whole time while we were mining and, no matter
what was happening, they turned their heads and looked away,"
Woody told the paper. "We poured four to six inches of concrete
where there was supposed to be 12, and they just turned their heads
away."
By the time the boulevard collapsed, the people
of Los Angeles were used to the sudden sinkage of parts of the famous
roadway. In August 1994, tunneling was halted on the Los Angeles Red
Line, the 4.4-mile stretch of subway that's supposed to be the
centerpiece of hundreds of miles of transit lines in the Metro rail
system. Sidewalks along Hollywood Boulevard above the project had
begun to sink and crack, eventually dropping up to 10 inches in some
places. An engineering firm hired by the MTA eventually reported that
the substitution of wood wedges for steel supports was approved by
engineers employed by Parsons Brinckerhoff and the project's
construction manager, Parsons-Dillingham. Parsons-Dillingham is a
partnership between Dillingham Construction and Parsons Corp., a
separate company with no relationship to the similarly named Parsons
Brinckerhoff. Parsons Corp. is a parent company of Parsons
Transportation Group, the consultants hired in 2000 by CATS and the
Charlotte City Council to do the engineering, environmental studies
and the planning for stations and land use for the South Boulevard
light rail line, for which they're being paid $5.8 million.
Multiple whistleblower lawsuits have shed some light on how
engineering snafus might have caused the hole in Hollywood Boulevard.
In 1994, Ben Pate, a former Metro Rail tunnel quality control
inspector, was awarded $1.38 million by a Superior Court jury in a
suit against his former employer, Parsons-Dillingham. In the suit, he
alleged he was fired for refusing to approve what he called "shoddy
and improper workmanship."
Engineer James Hamilton won a
settlement of $200,000 in a lawsuit against Parsons Dillingham and
the MTA's construction arm after claiming he was fired for raising
concerns about health and safety violations on the Metro Rail Line.
Another worker, Nelson McIntire, alleged that he was fired from the
project for exposing the threat of gas explosions and other safety
hazards on the construction site. McIntire's claim was settled for
less than $200,000.
But construction flaws were the least of
the MTA's problems with the two companies. By 1998, when
Parsons-Dillingham and EMC began wrapping up the project, it was $900
million over the original subway budget established in the mid-1980s
and MTA auditors still couldn't account for what happened to all the
money.
What is known is that 11 of the 12 design, engineering
and management contracts for the project grew from a starting price
of $227 million to $670 million; most of the cost increase -- $428
million - came from a contract with Parsons Dillingham for
construction oversight and a contract with EMC to design Metro Rail,
according to a report prepared for the Federal Transportation
Administration.
After questions were raised by the media
about the escalating costs of the project, the MTA put out a
statement which said that as the scope of rail projects was further
defined, the company's contracts were altered through change orders.
But the scope of those change orders was often staggering. An
investigation by The Daily News of Los Angeles found that in one
case, EMC initially reported committing just over $500,000 worth of
work to four subcontractors but wound up paying them over $43
million. In another case, an MTA inspector general's audit showed
that EMC billed $14 million for "unidentified subcontractors
doing unspecified work" on a rail line.
Accountant J.
Martin Gerlinger won a $300,000 settlement with Parsons Dillingham in
a suit in which he claimed he was fired after pointing out in a
meeting with supervisors that the firm had illegally overcharged the
MTA by $20 million.
How They Get Away With It
By now,
readers are probably wondering how these companies have managed to
stay afloat in the transit world and hang on to their contracts. The
answer to that question is a complex one.
Despite the
numerous scandals Parsons Brinckerhoff has weathered over the years,
the company has a rich history in American transit engineering. It
was responsible for the New York subway system, the Hoover Dam and
the Alaskan Oil pipeline. Since it was founded in 1885, it has been
one of the oldest continually operating consulting engineering firms
in the US and its more than 9,000 employees have been responsible for
thousands of projects on six continents. Ditto for Parsons Corp.,
whose more than 9,000 employees have been operating in 50 states and
40 foreign countries since the company was founded in 1944.
Over
time, the companies appear to have grown to be adept at two things:
manipulating the boards that oversee them and negotiating ambiguous,
open-ended contracts that make it difficult to fire them or hold them
responsible for anything that goes wrong on the project.
It's
not surprising that company money seems to find its way into the
pockets of politicians who oversee transit projects. A 1994 Los
Angeles Times investigation revealed that, over the previous decade,
the handful of elected officials who served on the MTA board --
similar to the MTC board here -- accepted more than $500,000 in
campaign contributions from subcontractors, lobbyists, lawyers and
other firms connected to Parsons-Dillingham and EMC. Former LA Mayor
Tom Bradley alone collected $45,000 from Metro Rail contractors.
Has it gone on here? How much if any money these companies
have donated to the six mayors from the Mecklenburg towns and cities
who sit on the MTC board here is hard to tell. The campaign reports
of Charlotte Mayor Pat McCrory and former county commission chair
Parks Helms, who chaired the MTC until recently, are riddled with
donations from individuals whose employer isn't listed, as the law
requires. During the 2002 election cycle, NC Senator Elizabeth Dole
accepted $5,000 from the Parsons Corp. PAC.
The firms'
ability to bond with the boards that oversee them seems to go beyond
just doling out campaign cash. Both firms are known for becoming so
intermeshed with the government transit agencies that hire them and
the transit boards that oversee them that it's difficult to tell
where one ends and the other begins. In California, some critics
refer to the MTA, the board that was supposed to be overseeing the
contractors, as a "front for the EMC." What they're trying
to describe is the almost eerie way in which public officials seem to
avoid any oversight of the contractors, even after embarrassing
public revelations that the companies were deliberately over-billing
them, withholding information from them or causing other problems.
At times, the sheer brazenness of the "Teflon
contractors" and the MTA's response to them was almost comical.
The same month Hollywood Boulevard caved in, for instance, MTA
auditors discovered, while auditing EMC's books, that the consortium
spent nearly $2 million of taxpayer money on changes to a planned
rail line in Pasadena without bothering to get MTA authorization. But
despite incidents like this, again and again public officials
overseeing both Big Dig and the Los Angeles Red Line turned their
heads, despite multiple promises to the public to fire them.
At
one point, MTA CEO Franklin White publicly vowed to cut
Parsons-Dillingham loose after federal officials threatened to
permanently take away over $1 billion in federal funding for the Red
Line. But it was White, not the companies, who would eventually lose
his job over the cost and construction fiascos on the project. While
Parsons-Dillingham did lose a part of its contract worth about $50
million as punishment, the MTA board went on to award them another
$58 million contract for three more portions of the Red Line. Despite
investigation reports that showed that EMC and Parsons-Dillingham
signed off on the wood-for-steel substitution, the MTA fired one of
their less-connected subcontractors for supposedly causing the fiasco
and then paid Parsons-Dillingham $7 million to oversee repairs to the
Hollywood streets the company was responsible for sinking. EMC was
paid nearly $900,000 to design sinkhole repair work.
In
Boston, where public officials have never bothered to attempt to
reclaim the tens of millions Bechtel-Parsons Brinckerhoff illegally
billed them for fixing its own design errors, the companies remain on
the job today.
Part of the problem here is that firing these
companies once they've become entrenched in a project isn't easy. In
August of 2001, Boston Turnpike Authority officials exploring ways to
boot Bechtel-Parsons Brinckerhoff from the project and still meet
their completion date ran into a common problem. There were only a
handful of firms in the world capable of completing the project, and
the long legal battle necessary to terminate the contract would have
dragged the project out even further. A similar thing happened in Los
Angeles after state legislators blasted MTA officials for allowing
Parsons Dillingham and EMC to stay on the job after numerous mishaps.
An Arthur Andersen audit concluded that the MTA would risk a bruising
court battle if it attempted to fire EMC because its contract was
riddled with "ambiguity." The MTA also discovered it
couldn't afford to dump Parsons-Dillingham either because the agency
needed the company on its side in court as it battled the more than a
thousand lawsuits the two companies left in their wake.
Perhaps
the most powerful asset these companies have in their court is their
political pull. Over time, the companies developed powerful federal
political connections they continue to nurture every year by donating
hundreds of thousands of dollars to national politicians and the two
political parties. Those connections in turn can be used to help
municipalities looking to win money in the highly competitive battle
for the federal transportation dollars without which most rail
projects, including ours, won't happen. Lobbying by Parsons
Brinckerhoff Chairman Marty Rubin in Washington in the 1980s was one
of the reasons Congress approved billions for the LA transit project
the company later worked on.
The companies' power appears to
extend far beyond just jockeying for federal dollars. Both appear to
be virtually immune to federal civil or criminal investigation. The
Los Angeles New Times reported in 1997 that investigations into the
Red Line announced by the FBI, the US Attorney's office and the US
Department of Transportation have never yielded any public results.
Ditto for the 2000 joint investigation launched by Federal Highway
Administration, FBI's Public Corruption Unit, the Department of Labor
and the Federal Department of Transportation -- an investigation that
was tainted by the state inspector general's report findings that Big
Dig project officials and Bechtel-Parsons had conspired with state
officials and the Federal Highway Administration to hide the true $14
billion cost of the project from the public. In fact, the vast
majority of the dirt that's been uncovered on both projects has been
the result of investigations by the media, by independent state
auditors or inspectors or by the boards that oversaw these projects
after public opinion demanded it.
Where the Money Goes,
Nobody Knows
Given the history of large transit projects
around the world, it may be that officials everywhere have trouble
getting a handle on the half-dozen or so construction companies in
the world capable of overseeing the creation of mass transit systems.
In a worldwide study of the cost estimating on 258 transit projects
called "Underestimating Costs in Public Works Projects: Error or
Lie?" Danish professor Bent Flyvbjerg and his colleagues found
that underestimating costs and overestimating rail ridership in
initial studies of whether an area needs a mass transit system seems
to be an industry tradition. In 9 out of 10 transportation
infrastructure projects, Flyvbjerg found, costs are underestimated
and for rail projects actual costs are on average 45 percent higher
than estimated costs. The situation is not a product of lack of
experience with a certain type of transit, either. The average
percentage by which the cost of these projects is underestimated
hasn't varied in 30 years. Excluding cases in which major design
changes were made as the project went along, Flyvbjerg found that
project promoters routinely "ignore, hide, or otherwise leave
out important project costs and risks in order to make total costs
appear low" and sell the public on the project.
Overseeing
companies this powerful, experienced and well connected isn't easy
for any municipality working on a transit project. Most of the cost
overruns on American transit projects come in the form of change
orders that alter the original contract of the contractors working on
the project. To have 10 to 20 percent of the project's final cost
come from change orders is fairly standard in the transit
construction industry. On a project like Charlotte-Mecklenburg's with
a $2.1 billion price tag, the documentation on change orders can fill
whole rooms and require a full-time staff just to process.
Over-billing by contractors is another way millions of dollars can go
out the door undetected. That, too, requires a full staff of auditors
to keep up with. Without this kind of structured oversight, things go
awry. MTA officials still can't account for what happened to all of
the $900 million in cost overruns on the Red Line and Big Dig
officials have forfeited millions of unaccounted-for dollars to
contractors because the statute of limitations on filing claims to
get the money back has run out.
Have a comment about the
site? Send them to Us Charlotte's Creative Loafing
Copyright ©
2003 Creative Loafing Charlotte, Inc.